* Averaging Initial Base Readings
Posted by on 07 December 2011 11:46 AM
|
|
1. Introduction This guide details the method for averaging multiple base readings for a borehole. It is recommended that at least 3 borehole runs are initially taken for a new borehole these can then be averaged using the In-Site software for a more accurate base reading.
2. Averaging Multiple Base Readings in In-Site
Figure 1. Make A New Averaging Survey
Figure 2. Select 'Generate'
Tip: If borehole runs are averaged and none of them are the first reading set, the generated file will still be dated as the initial reading. The date can then be changed if creating an initial reading is not the purpose of the average.
If you have any queries about the above information, please submit a ticket through the support site or call Soil Instruments on +44 01825 765044 for advice. Checked MO'R v1.0 19/05/15 | |
|